Dears
We would to set up EPC plant for 12 KTY, P4 yellow phosphorus plant, included: Engineering, equipment and construction supervision & design, installation plus commissioning
50% from production will be converted to phosphoric acid food grade 85%
Your quotation should include:
1-Equipment list such as: Submerged arc furnace, electric transformers, gas towers cleaning, up cranes 30 and 5 tons, pumps 60 m3 \hour, Slag crucible, control board, dryers, hydrator, Trucks, loaders and Clark cranes
. 2-Required land area
. 3-Estimated civil works design and "concrete m3" and roads length
. 4-Required labor " staff" and types
. 5-Laboratory equipment
. 6-steam section
7-Packing system
. 8-Rock Handling System
. 9-Reaction Section
. Filtration Section10-
11- 24month recommended spare parts estimated cost
. 12-installation cost
Environment protection system13-
Our proposed. Raw material consumption index for 1t yellow phosphorus:
Rock phosphate Base 24%, 11 ton-
Coke Base on C84%, 1.65 ton
Silica Base on SiO299%. 95 ton
Electrode 30 kg
Thanks and regards
AEGCC" Arab Egyptian Gas & Chemicals Co"
Mohamed EL Sharkawy
3, Gol Gamal street, flat #8, Mohandessin, Gizah, Egypt